Capital Project Timeline

2017-18 Capital Outlay Project

  • $100,000

    • Currently submitted to SED
    • Fall 2017 - Request for Bids
    • Spring 2018 - Anticipated work to begin

2016 Capital Project

  • $8,700,000

    • Currently submitted to SED
    • March 2018 - Anticipated approval from SED
    • April 2018 - Request for bids/awards contracts
    • June 2018 - Construction begins
    • September 2019 - Substantial completion of work
    • November 2019 - Closeout

SMART BOND Technology

  • $601,000

    • Currently submitted to SED
    • Spring 2018 - Anticipated approval from SED
    • Summer 2018 - Installation and completion of technology upgrades

Energy Performance Contract (EPC)

  • $1,129,074

    • October 2017 - Received SED approval
    • November 2017 - Work begins 
    • March 2018 - Work is completed